Backlog reduction
46%
Closed workorders92
Original backlog200
New backlog108
Treated
75%
150 of 200 workorders · last 10 weeks
Decision distribution
150treated
- Confirmed close9261%
- Keep open3825%
- To review2013%
Closed workorders breakdown
Closed workorders
Backlog group
Label
Days open group
Progress per discipline
Cleaning
0/9
0%Electrical
2/13
15%Instrumentation
1/14
7%Insulation
0/9
0%Rotating
5/22
23%Static
4/23
17%Closed Workorders Breakdown
7
Workorders in Selection
Preventive
Period workorder was open
A) <2 months
B) 2-6 months
1
C) 6-12 months
2
D) 12-24 months
3
E) >24 months
1
Priority of the workorders
1
1
4
1
Year scheduled
20232025
Process violations · 37 workorders
Workorders flagged as “work done” — where are they sitting?
Filtered on labels monitoring, work_done, punch_items, partly_executed.in executionscheduledelsewhere = violation
| Discipline | New | Planning in Progress | Planned | Ready for Scheduling | Scheduled | Work in Progress | Total |
|---|---|---|---|---|---|---|---|
| Cleaning | 1 | · | 1 | · | 1 | · | 3 |
| Electrical | 2 | · | 1 | · | 2 | · | 5 |
| Instrumentation | 2 | 1 | 1 | · | · | 1 | 5 |
| Insulation | 2 | · | 1 | · | · | · | 3 |
| Rotating | · | 1 | 2 | · | 3 | 4 | 10 |
| Static | 4 | · | 2 | · | 2 | 3 | 11 |
| Total | 11 | 2 | 8 | · | 8 | 8 | 37 |